Bond Dollars at Work
Preschool
(One Bloomin' Preschool program site will be located in the building that currently houses Eastover Elementary - please reference the "Conant" tab to see the improvements scheduled for the Bloomin' Preschool Conant location)
Year built: 1955 (age of building: 65 years old)
Proposed Bond Program Costs: $9.2M
Proposed Start Date: Summer 2023
Proposed Completion Date: Fall 2025
Safety/Security/ADA/Code
- create secure entry vestibule
- improve playground (including accessibility)
- upgrade interior classroom door hardware
- install fire suppression system
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- add door contacts to exterior doors
- upgrade intrusion detection system
Educational Improvements
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- assess and replace select classroom furniture
Community Improvements
-
renovate classrooms for early childhood program
Critical Infrastructure
- parking lot improvements
- roofing work
- replace select interior doors
- replace select ceilings
- replace select flooring
- replace select mechanical equipment
- upgrade select interior lighting
Elementary School
Conant
Year built: 1960 (age of building: 60 years old)
Proposed Bond Program Costs: $16.7M
Proposed Start Date: Summer 2022
Completion Date: Fall 2024
Safety/Security/ADA/Code
- create secure entry vestibule
- improve playground (including accessibility)
- upgrade interior classroom door hardware
- install fire suppression system
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- add door contacts to exterior doors
- upgrade intrusion detection system
Educational Improvements
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- assess and replace select classroom furniture
Community Improvements
-
renovate classrooms for early childhood program
Critical Infrastructure
- parking lot improvements
- roofing work
- replace select interior doors
- replace select ceilings
- replace select flooring
- replace select mechanical equipment
- upgrade select interior lighting
Eastover
(Eastover will move into the building that currently houses East Hills Middle School)
Year built: 1962 (age of building: 58 years old)
Proposed Bond Program Costs: $13.4M
Proposed Start Date: Spring 2022
Proposed Completion Date: Fall 2024
Safety/Security/ADA/Code
- create secure entry vestibule
- improve parking lot traffic flow
- improve playground (including accessibility)
- upgrade interior classroom door hardware
- install fire suppression system
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- upgrade intrusion detection system
Educational Improvements
-
improve art and music rooms
-
renovate special needs spaces
-
upgrade teaching wall in classrooms
-
upgrade network infrastructure
-
upgrade wireless infrastructure
-
upgrade classroom sound systems
-
replace student and teacher devices
-
replace classroom audio/visual system
-
replace select classroom furniture
Critical Infrastructure
-
repave partial parking lot
- replace select roofing
- replace select interior doors
- replace select ceilings
- replace select flooring
- replace select classroom casework
- replace select mechanical equipment
- upgrade select interior lighting
Lone Pine
(Lone Pine will move into the building that currently houses West Hills Middle School)
Year built: 1966 (age of building: 54 years old)
Proposed Bond Program Costs: $10.7M
Proposed Start Date: Spring 2022
Completion Date: Fall 2024
Safety/Security/ADA/Code
- create secure entry vestibule
- improve parking lot traffic flow
- improve playground (including accessibility)
- upgrade interior classroom door hardware
- install fire suppression system
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- upgrade intrusion detection system
Educational Improvements
- improve art and music rooms
- renovate special needs spaces
- upgrade teaching wall in classrooms
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace select classroom furniture
Critical Infrastructure
-
replace select concrete walks
- replace select roofing
- replace select interior doors
- replace select ceilings
- replace select flooring
- replace select classroom casework
- replace select mechanical equipment
- upgrade select interior lighting
Way
Year built: 1966 (age of building: 54 years old)
Proposed Bond Program Costs: $12.4M
Proposed Start Date: Spring 2022
Completion Date: Fall 2024
Safety/Security/ADA/Code
-
create secure entry vestibule
- improve parking lot traffic flow
- improve playground (including accessibility)
- upgrade interior classroom door hardware
- install fire suppression system
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- upgrade intrusion detection system
Educational Improvements
-
build additional classrooms
- build multi-purpose room
- improve art and music rooms
- renovate special needs spaces
- upgrade teaching wall in classrooms
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace select classroom furniture
Critical Infrastructure
-
replace select concrete walks
- replace select roofing
- replace select interior doors
- replace select ceilings
- replace select flooring
- replace select classroom casework and install student lockers
- replace select mechanical equipment
- upgrade select interior lighting
Middle School
North Hills Middle School
(North Hills will be housed in the building that formerly served as Lahser High School)
Year built: 1967 (age of building: 53 years old)
Proposed Bond Program Costs: $55.2M
Proposed Start Date: Summer 2021
Proposed Completion Date: Fall 2023
Safety/Security/ADA/Code
- create secure entry vestibule
- upgrade interior classroom door hardware
- install fire suppression system
- upgrade parking lot lighting
- upgrade exterior building lighting
Educational Improvements
- build classroom additions
- build multi-purpose commons space
- improve art and music rooms
- renovate special needs spaces
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace classroom furniture
Community Improvements
-
natatorium (pool)
Critical Infrastructure
- redesign select parking lots
- replace select concrete walks
- replace select roofing
- replace select interior doors
- replace select ceilings
- replace select flooring
- replace select mechanical equipment
- upgrade select interior lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- upgrade intrusion detection system
South Hills Middle School
(South Hills will occupy the building that currently houses Bloomfield Hills Middle School)
Year built: 1958 (age of building: 62 years old)
Proposed Bond Program Costs: $38.9M
Proposed Start Date: Summer 2021
Completion Date: Spring 2024
Safety/Security/ADA/Code
-
create secure entry vestibule
-
improve parking lot traffic flow
- upgrade interior classroom door hardware
- install fire suppression system
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- upgrade intrusion detection system
Educational Improvements
- build science rooms
- build arts and auditorium addition
- renovate special needs spaces
- upgrade teaching wall in classrooms
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace classroom furniture
Community Improvements
- install synthetic turf fields
- install turf in fieldhouse
Critical Infrastructure
- redesign parking lot
- replace select concrete walks
- replace select roofing
- replace select interior doors
- replace select ceilings
- replace select flooring
- replace select classroom casework
- replace select mechanical equipment
- upgrade select interior lighting
High School
Bloomfield Hills High School
2/3 of the building was constructed in 2015 (age of building: 5 years old)
Proposed Bond Program Costs: $18.0M
Proposed Start Date: Summer 2023
Proposed Completion Date: Fall 2026
Safety/Security/ADA/Code
-
expand video surveillance system
-
upgrade access control
-
upgrade public address systems
Educational Improvements
-
upgrade network infrastructure
-
upgrade wireless infrastructure
-
upgrade classroom sound systems
-
replace student and teacher devices
-
replace classroom audio/visual system
-
replace classroom furniture
Community Improvements
-
build wellness center
-
construct concession/restroom building
-
install turf on baseball & softball field
Critical Infrastructure
-
replace select roofing section
-
replace select interior doors
-
replace select classroom casework
Traub (Current location of IA Okma)
Year built: 1965 (age of building: 55 years old)
Proposed Bond Program Costs: $2.3M
Proposed Start Date: Spring 2025
Completion Date: Fall 2025
Safety/Security/ADA/Code
-
create secure entry
-
upgrade access control
-
upgrade public address systems
-
upgrade intrusion detection system
Educational Improvements
-
upgrade network infrastructure
-
upgrade wireless infrastructure
Critical Infrastructure
-
replace select interior doors
- upgrade select windows
- replace select flooring
- replace select mechanical equipment
Wing Lake Developmental Center
Year built: 2008 (age of building: 12 years old)
Proposed Bond Program Costs: $0.7M
Proposed Start Date: Summer 2025
Proposed Completion Date: Fall 2025
Safety/Security/ADA/Code
-
create secure entry vestibule
-
upgrade access control
-
upgrade public address systems
Educational Improvements
-
upgrade network infrastructure
-
upgrade wireless infrastructure
Critical Infrastructure
-
replace select mechanical equipment
More District Buildings
- Bowers School Farm
- Johnson Nature Center
- Booth Center (Central Office & PREP)
- Transportation & Maintenance
Bowers School Farm
Year built: 2010 (age of building: 20 years old)
Proposed Bond Program Costs: $4.6M
Proposed Start Date: Spring 2025
Completion Date: Spring 2026
Safety/Security/ADA/Code
-
install video surveillance system
-
upgrade access control
-
upgrade public address systems
Educational Improvements
-
upgrade network infrastructure
-
upgrade wireless infrastructure
-
upgrade classroom sound systems
-
replace student and teacher devices
-
replace classroom audio/visual system
-
replace classroom furniture
Community Improvements
-
build equestrian pavilion
-
build livestock learning lab
-
expand parking lot
-
improve barn structure
-
improve cottage
-
add pavilion
Critical Infrastructure
-
repave parking lot
-
upgrade site utilities and drainage
Johnson Nature Center
Visitor Center Year built: 2006
Proposed Bond Program Costs: $0.7M
Proposed Start Date: Summer 2025
Proposed Completion Date: Fall 2025
Safety/Security/ADA/Code
- add accessible walkways
- upgrade parking lot lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- upgrade intrusion detection system
Educational Improvements
-
upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace audio/visual system
- replace select furniture
Critical Infrastructure
-
install curbs at parking lot
-
replace gates
-
improve select windows
Booth Center (Central Office & PREP)
Year built: 1962 (age of building: 58 years old)
Proposed Bond Program Costs: $2.9M
Proposed Start Date: Spring 2026
Proposed Completion Date: Fall 2026
Safety/Security/ADA/Code
-
improve entrance configuration
-
install video surveillance system
-
upgrade access control
-
upgrade intrusion detection system
Critical Infrastructure
-
improve site drainage
-
replace roofing
-
replace mechanical equipment
-
upgrade electrical panels