  • Wood doors installed and concrete work underway
  • Final inspections and occupancy are coming soon, with the goal of opening for the start of the 2025-26 school year. 
  • Join us for the official ribbon cutting of the new BHHS Wellness Center! All Bloomfield Hills Schools families and staff are warmly invited to this exciting community celebration. Come explore the stunning new Wellness Center and athletic facilities. RSVP here.

BHHS Wellness Center Ribbon Cutting Celebration
Friday, September 12, 2025, 5:30 p.m.
Bloomfield Hills High School – Andover Road

Athletic Restrooms & Stadium Entrance

  • Canopy installation is underway
  • Mechanical, electrical, and plumbing work in progress
  • Upcoming work includes handrail and fencing updates
     

BHS Track Renovations

  • Demolition is complete
  • Resurfacing and painting will start end of July 
  • The Track and Field will be closed to all activities except those that have been pre-approved. In order to get approval, or if you have any questions, please don’t hesitate to reach out to Avis Najor or Mike Cowdrey.
     

Fox Hills Demolition

  • Water main capped and site restoration nearly finished
  • The building was demolished and this location will continue to have a parking lot and allow for considerable greenspace. 

Elementary Schools

  • Construction is currently on time at all four elementary schools 
  • Construction is progressing across all elementary schools this summer: Conant is framing new walls and demolition is nearly complete, Eastover is nearing the end of demolition with painting underway and flooring to begin soon, Lone Pine has completed media center work and is preparing for front entrance upgrades, and Way has begun carpet installation in the fine arts wing while addressing door updates.

International Academy

  • New windows and demolition completed
  • Main office construction on schedule
     

Wing Lake Development Center

  • Major tech upgrades completed: new IFPs, sound systems, data runs, and desktops
  • Secure vestibule doors being installed
     

Robotics & Bloomin’ West

Framing complete and steel decking underway

Quarterly update presented at the Board of Education meeting on July 28, 2025.