Way Elementary Animation of Bond Work Plans
Conant Elementary Animation of Bond Work Plans
School Building Details
Conant
Year built: 1960 (age of building: 60 years old)
Proposed Bond Program Costs: $16.7M
Proposed Start Date: Summer 2022
Completion Date: Fall 2024
Safety/Security/ADA/Code
- create secure entry vestibule
- improve parking lot traffic flow
- improve playground (including accessibility)
- upgrade interior classroom door hardware
- install fire suppression system
- add emergency generator connection
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- add door contacts to exterior doors
- upgrade intrusion detection system
Educational Improvements
- build additional classrooms
- build multi-purpose room
- improve art and music rooms
- renovate special needs spaces
- upgrade teaching wall in classrooms
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace classroom furniture
Community Improvements
-
expand early childhood center
Critical Infrastructure
- reconfigure parking lot and bus loop
- replace concrete walks
- replace roofing
- replace select interior doors
- replace ceilings
- replace flooring
- replace classroom casework
- replace mechanical equipment
- upgrade interior lighting
Eastover
(Eastover will move into the building that currently houses East Hills Middle School)
Year built: 1962 (age of building: 58 years old)
Proposed Bond Program Costs: $13.4M
Proposed Start Date: Spring 2022
Proposed Completion Date: Fall 2024
Safety/Security/ADA/Code
- create secure entry vestibule
- improve parking lot traffic flow
- improve playground (including accessibility)
- upgrade interior classroom door hardware
- install fire suppression system
- add emergency generator connection
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- add door contacts to exterior doors
- upgrade intrusion detection system
Educational Improvements
- improve art and music rooms
- renovate special needs spaces
- upgrade teaching wall in classrooms
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace classroom furniture
Community Improvements
-
install turf in fieldhouse
Critical Infrastructure
- repave parking lot
- replace roofing
- replace interior doors
- replace ceilings
- replace flooring
- replace classroom casework
- replace mechanical equipment
- upgrade interior lighting
Lone Pine
(Lone Pine will move into the building that currently houses West Hills Middle School)
Year built: 1966 (age of building: 54 years old)
Proposed Bond Program Costs: $10.7M
Proposed Start Date: Spring 2022
Completion Date: Fall 2024
Safety/Security/ADA/Code
- create secure entry vestibule
- improve parking lot traffic flow
- improve playground (including accessibility)
- upgrade interior classroom door hardware
- install fire suppression system
- add emergency generator connection
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- add door contacts to exterior doors
- upgrade intrusion detection system
Educational Improvements
- improve art and music rooms
- renovate special needs spaces
- upgrade teaching wall in classrooms
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace classroom furniture
Community Improvements
-
install turf in fieldhouse
Critical Infrastructure
- replace concrete walks
- replace roofing
- replace interior doors
- replace ceilings
- replace flooring
- replace classroom casework
- replace mechanical equipment
- upgrade interior lighting
Way
Year built: 1966 (age of building: 54 years old)
Proposed Bond Program Costs: $12.4M
Proposed Start Date: Spring 2022
Completion Date: Fall 2024
Safety/Security/ADA/Code
- create secure entry vestibule
- improve parking lot traffic flow
- improve playground (including accessibility)
- upgrade interior classroom door hardware
- install fire suppression system
- add emergency generator connection
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- install video surveillance system
- upgrade access control
- upgrade public address systems
- add door contacts to exterior doors
- upgrade intrusion detection system
Educational Improvements
- build additional classrooms
- build multi-purpose room
- improve art and music rooms
- renovate special needs spaces
- upgrade teaching wall in classrooms
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace classroom furniture
Critical Infrastructure
- replace concrete walks
- replace roofing
- replace interior doors
- replace ceilings
- replace flooring
- replace classroom casework and add student cubbies
- replace mechanical equipment
- upgrade interior lighting