North Hills Middle School
(North Hills will be housed in the building that formerly served as Lahser High School)
Year built: 1967 (age of building: 53 years old)
Proposed Bond Program Costs: $55.2M
Proposed Start Date: Summer 2021
Proposed Completion Date: Fall 2023
Safety/Security/ADA/Code
- create secure entry vestibule
- upgrade interior classroom door hardware
- install fire suppression system
- upgrade parking lot lighting
- upgrade exterior building lighting
Educational Improvements
- build classroom additions
- build multi-purpose commons space
- improve art and music rooms
- renovate special needs spaces
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace classroom furniture
Community Improvements
-
natatorium (pool)
Critical Infrastructure
- redesign select parking lots
- replace select concrete walks
- replace select roofing
- replace select interior doors
- replace select ceilings
- replace select flooring
- replace select mechanical equipment
- upgrade select interior lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- upgrade intrusion detection system
South Hills Middle School
(South Hills will occupy the building that currently houses Bloomfield Hills Middle School)
Year built: 1958 (age of building: 62 years old)
Proposed Bond Program Costs: $38.9M
Proposed Start Date: Summer 2021
Completion Date: Spring 2024
Safety/Security/ADA/Code
- create secure entry vestibule
- improve parking lot traffic flow
- upgrade interior classroom door hardware
- install fire suppression system
- upgrade parking lot lighting
- upgrade exterior building lighting
- install video surveillance system
- upgrade access control
- upgrade public address systems
- upgrade intrusion detection system
Educational Improvements
- build science rooms
- build arts and auditorium addition
- renovate special needs spaces
- upgrade teaching wall in classrooms
- upgrade network infrastructure
- upgrade wireless infrastructure
- upgrade classroom sound systems
- replace student and teacher devices
- replace classroom audio/visual system
- replace classroom furniture
Community Improvements
- install synthetic turf fields
- install turf in fieldhouse
Critical Infrastructure
- redesign parking lot
- replace select concrete walks
- replace select roofing
- replace select interior doors
- replace select ceilings
- replace select flooring
- replace select classroom casework
- replace select mechanical equipment
- upgrade select interior lighting